Question: If the variable overhead efficiency variance is favorable then which of the following must be true. A . Actual hours is greater than standard hours.
If the variable overhead efficiency variance is favorable then which of the following must be true.
A Actual hours is greater than standard hours.
B Actual output is greater than planned output.
C Actual output is less than planned output.
D Variable overhead is under applied.
E None of the above.
Using a standard cost system, if planned budgeted machine hours were and standard hours SH were which of the following must be true?
a Variable overhead was underapplied
b The spending variance is favorable
c The efficiency variance is unfavorable
d Variable overhead was overapplied
e None of the above.