Question: If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned

If three workers are assigned to a task lasting

If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days. The tasks can be completed independently of each other. If you are to schedule with a resource-limit, what is the minimum resource limit for the project? Three workers per day Seven days Additional information is needed to determine the minimum number 21 worker-days