Question: If two tasks have a resource conflict ( i . e . both must be completed by the same person and cannot be completed at

If two tasks have a resource conflict (i.e. both must be completed by the same person and cannot be completed at the same time), how should a PM decide which to schedule first and which to move to a later date?
One way to minimize resource conflicts is to organize resources into pools, groups of resources who are interchangeable in scheduling. For example, instead of having Professor David and Professor Lu each available 40 hours/week, you could have a pool called "Professors" available for 80 hours/week. What are the advantages and disadvantages of this approach?
What are some of the barriers to implementing critical chain concepts in the real world?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!