Question: if unit 1 requires 8 labor hours and unit 4 requires 5.78. What have the first 7 units required in total? A. not greater than
if unit 1 requires 8 labor hours and unit 4 requires 5.78. What have the first 7 units required in total?
A. not greater than 35
B. greater than 45, not greater than 50
C. greater than 40, not greater than 45
D. greater than 35, not greater than 40