Question: If workpieces are completed in a workstation in a batch of 100 and setup time is 2 minutes and run time is 0.2 minute per
If workpieces are completed in a workstation in a batch of 100 and setup time is 2 minutes and run time is 0.2 minute per unit, a. what is the production rate? b. If the batch size is halved, what's its impact in production rate?
Please provide step by step explanation with numerical answers instead of unnencessary theory.
Step by Step Solution
There are 3 Steps involved in it