Question: If you had to allow one task to slip on a project, which of the following tasks would be the BEST to allow to slip

If you had to allow one task to slip on a project, which of the following tasks would be the BEST to allow to slip (take more time)?Select one:A task with slackA task with total floatA task with free floatA task on the critical.path