if you have the following information for three projectsA ,B ,and C.
t A B C
0 ($50,000) $(100,000) ($450,000)
1 $10,000 $25,000 $200,000
2 $15,000 $25,000 $200,000
3 $20,000 $25,000 $200,000
4 $25,000 $25,000
5 30,000 $25,000
a. Calculate the NPV for the three projects considering the required return 10%? And 20%
b. In each case (Required return 10% and 20%) what is your decisionif :
-The projects independent?
- The projects mutually exclusive?
c. Calculatethe Payback period, and decide which project you will choose?