Question: a) Effort Driven Scheduling is one of the features available in Microsoft Project. Explain how effort-driven schedule functions in Microsoft Project. (6 Marks) b) Elaborate

a) "Effort Driven Scheduling" is one of the features available in Microsoft Project. Explain how effort-driven schedule functions in Microsoft Project. (6 Marks)

b) Elaborate on the function of "Accrue at" in the resource sheet of Microsoft Project.(6 Marks)

Step by Step Solution

3.43 Rating (143 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

ANSWERA One of the features of the Microsoft Project is Effort Driven Scheduling Explain how Microso... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

635e3f47bb789_183177.pdf

180 KBs PDF File

Word file Icon

635e3f47bb789_183177.docx

120 KBs Word File

Students Have Also Explored These Related General Management Questions!