If you recall, your company needed to choose between two projects, C and D, and each required
Fantastic news! We've Found the answer you've been seeking!
Question:
If you recall, your company needed to choose between two projects, C and D, and each required a $10,000,000 investment. Your discount rate was 8%. As a reminder, these were the forecasted cash flows:
Project C | Project D | |
---|---|---|
Year 0 | ($10,000,000) | ($10,000,000) |
Year 1 | $1,500,000 | $9,000,000 |
Year 2 | $2,000,000 | $3,000,000 |
Year 3 | $2,500,000 | $1,200,000 |
Year 4 | $5,000,000 | $0 |
Year 5 | $5,000,000 | $0 |
We said the net present value of Project C was $2,166,210 and the NPV of Project D was $1,857,950. The IRR of Project C is 14.3% and the IRR of project D is 22.5%.
Which project would you choose and why?