Question: If you would like to base your project time estimate using similar past projects, which time estimation technique would you use?Required to answer. Single choice.
If you would like to base your project time estimate using similar past projects, which time estimation technique would you use?Required to answer. Single choice.
(1 Point)
One-Point Estimating.
Three-Point Estimating.
Analogous Estimating.
Critical Path Estimation.
Parametric Estimating.
Step by Step Solution