Question: If your project is fully funded - you are provided all of the funds requested for the baseline project plan - it may not be
-
If your project is fully funded - you are provided all of the funds requested for the baseline project plan - it may not be enough. One of the key reasons is that management reserves are not usually put into the project baseline funding for unknown unknowns.
True
False