Question: ii ) Consider the following schedules : S 1 : r 1 ( w ) , w 1 ( x ) , r 1 (

ii) Consider the following schedules :
S1: r1(w),w1(x),r1(y),w1(y),r1(x),w2(x),c2,c1
S2: r1(x),w1(x),r2(x),r1(y),w2(x),w1(y),c1,c2
Which schedule is recoverable explain in steps and graphs if needed? (6 marks)
 ii) Consider the following schedules : S1: r1(w),w1(x),r1(y),w1(y),r1(x),w2(x),c2,c1 S2: r1(x),w1(x),r2(x),r1(y),w2(x),w1(y),c1,c2 Which