Question: II . Process Flow Diagram for Making a Shirt, with an Additional Worker All steps ( A , B , C , D , and

II. Process Flow Diagram for Making a Shirt, with an Additional Worker
All steps (A, B, C, D, and E) in the below process are necessary to create each finished unit. Task times are shown for each step. A second worker has been hired to duplicate task D. Now shirts that have been through task C go to any one of the two workers on task D . The product still requires the five steps (A,B,C,D,E.
10 mins./unit
12 mins./unit
3. Refer to the Process Flow Diagram for Making a Shirt, with an Additional Worker. Assume the entire process is running at the pace of the bottleneck. Consider only task D, with both workers ironing shirts. What is the capacity utilization for ironing?
4. Refer to the Process Flow Diagram for Making a Shirt, with an Additional Worker. What is the minimum throughput time, that is, the fastest a rush order of one unit can go through the process?
 II. Process Flow Diagram for Making a Shirt, with an Additional

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!