Question: ii ) table [ [ Activity , table [ [ Normal duration ] , [ ( weeks ) ] ] , table

ii)
\table[[Activity,\table[[Normal duration],[(weeks)]],\table[[Normal cost],[(Rs)]],\table[[Crash duration],[(weeks)]],\table[[Crash cost],[(Rs)]]],[1-2,5,3000,2,10000],[2-3,6,4000,2,7000],[2-4,7,3500,4,5000],[3-4,5,5000,2,8000]]
The project overhead costs are Rs 2500 per week. Find the optimum duration and the cost associated with it. Draw also the least cost network.
 ii) \table[[Activity,\table[[Normal duration],[(weeks)]],\table[[Normal cost],[(Rs)]],\table[[Crash duration],[(weeks)]],\table[[Crash cost],[(Rs)]]],[1-2,5,3000,2,10000],[2-3,6,4000,2,7000],[2-4,7,3500,4,5000],[3-4,5,5000,2,8000]] The project overhead costs are