A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of units per day. The tasks necessary to produce this product
tableTaskPredecessor,uTime secondsvuwuwvis,
If the company desires that output rate equal demand, what is the minimum number of workstations needed?