Question: III. Problem Solving (25 points) The AMAG Inc has the following activities of a project for a corporation. a. Construct a Network Diagram b. Determine
III. Problem Solving (25 points) The AMAG Inc has the following activities of a project for a corporation. a. Construct a Network Diagram b. Determine the project duration C. Identify the critical path d. Construct a Gantt Chart for this project. When will the project end if it will start on January 8, 2024 (all Sundays are restdays and are not included in the schedule). Activity A B C D E F G H I Immediate Predecessors None A A B B C E,F D G,H Duration (Weeks) 9 7 3

6 9 4 6 5 3


The AMAG Inc has the following activities of a project for a corporation. a. Construct a Network Diagram b. Determine the project duration c. Identify the critical path d. Construct a Gantt Chart for this project. When will the project end if it will start on January 8, 2024 (all Sundays are restdays and are not included in the schedule). The AMAG Inc has the following activities of a project for a corporation. a. Construct a Network Diagram b. Determine the project duration c. Identify the critical path d. Construct a Gantt Chart for this project. When will the project end if it will start on January 8, 2024 (all Sundays are restdays and a not included in the schedule). The AMAG Inc has the following activities of a project for a corporation. a. Construct a Network Diagram b. Determine the project duration c. Identify the critical path d. Construct a Gantt Chart for this project. When will the project end if it will start on January 8, 2024 (all Sundays are restdays and are not included in the schedule)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts