Question: -------------- Illustrates the expected resource use by time period? * 1 point Schedule table Resource requirement plan Resource experience list All of the above --------is

-------------- Illustrates the expected resource use by time period? *

1 point

Schedule table

Resource requirement plan

Resource experience list

All of the above

--------is informally making changes to the project scope without appropriate approval. *

1 point

Product log

Change control

Scope creep

Risk registry

Which of the following is the correct statement? *

1 point

LS= LF- Estimated Duration

LS= Estimated duration - LF

LS = ES+EF

All of the above