Question: I'm not sure what more data do you need, because this is EVERYTHING that has been provided to me, so at the end of this


I'm not sure what more data do you need, because this is EVERYTHING that has been provided to me, so at the end of this assignment, your answer should looks like the example shown in the second screenshot.
Consider the following project network, and answer questions 1, 2, and 3 . 1. For each activity, find the earliest start (ES) date, the earliest finish (EF) date, the latest start (LS) date and the latest finish (LF) date. (Assume the project due date is set to be the earliest possible completion time of the project.) 2. For each activity calculate the total slack and the free slack. 3. Identify the critical path of the project
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
