Question: Imagine you are a programmer that receives requests each week to analyze a large data base. Five jobs are on your desk Monday morning and
Imagine you are a programmer that receives requests each week to analyze a large data base. Five jobs are on your desk Monday morning and you need to decide in what order you will do the jobs. Assume the jobs all arrived on Monday morning (day 1 and hour 1) in the order shown below. You have predicted the number of hours each job will take.

Part a. You want to determine the sequence according to the following decision rules:
FCFS (First Come First Serve): Type in the sequence of jobs _________________
EDD (Earliest Due Date): Type in the sequence of jobs _________________
SPT (Shortest Process Time): Type in the sequence of jobs _________________
Part b. Complete the below table showing the performance metrics for each rule:
| Rule | Avg Flow Time | Avg Lateness | Avg # Jobs |
| FCFS | |||
| EDD | |||
| SPT |
Part c. Which decision rule is best (type in either FCFS, EDD, or SPT): ________
JOB DUE DATE (HOURS HENCE) 12 DURATION (HOURS REQUIRED) 7 A 8 6 B 18 3 D 14 28 24 E 10Step by Step Solution