Question: Immediate Activity Predecessor ( s ) Pessimistic Probable Optimistic table [ [ J , - - , 1 5 , 1 0 , 8
Immediate
Activity Predecessors Pessimistic Probable Optimistic
tableJNKM
a Calculate the expected duration of each activity.
b Calculate the expected duration and variance of the critical path.
c Calculate the probability that the project will be completed in fewer than time units.