Question: Immediate Activity time Activity Activity Description Predecessor (days) A Identify Client Base 28 Develop Client B 32 Prospectus Perform Design C 49 Analysis D Program

 Immediate Activity time Activity Activity Description Predecessor (days) A Identify Client

Base 28 Develop Client B 32 Prospectus Perform Design C 49 Analysis

Immediate Activity time Activity Activity Description Predecessor (days) A Identify Client Base 28 Develop Client B 32 Prospectus Perform Design C 49 Analysis D Program Back End A, B, C 14 E Program Front End A 44 F Project Consolidation D, E 16 (a) For the given project, fill in the nodes of the network diagram below. A E 28 44 Start D F Finish Time 32 14 16 Time C 49