Question: Immediate Normal Minimum ACTIVITY Crash Costs Predecessor Duration (wks) Duration (wks) ($/wk) 4 4 -- B 3 2 100 AB 5 3 200 D E

Immediate Normal Minimum ACTIVITY Crash Costs
Immediate Normal Minimum ACTIVITY Crash Costs
Immediate Normal Minimum ACTIVITY Crash Costs Predecessor Duration (wks) Duration (wks) ($/wk) 4 4 -- B 3 2 100 AB 5 3 200 D E c 2 300 F 1 1 G D 3 200 H E 1 1 1 1 1 1 . 1 100 What is the slack time for Activity F and the late start for Activity H? O 2 weeks, 11 weeks 0 1 weeks, 11 weeks O 3 weeks, 10 weeks O 2 weeks, 12 weeks O None of the above are correct