Question: Immediate Predecessors a b M 2 Activity A B D E F 2 Description Find site Find engineers Hire opening act Set radio and TV

Immediate Predecessors a b M 2 Activity A B D E F

Immediate Predecessors a b M 2 Activity A B D E F 2 Description Find site Find engineers Hire opening act Set radio and TV ads Set up ticket agents Prepare electronics Print advertising Set up transportation Rehearsals Last-minute details 1 A A A B F, 1 4 3 3 2 10 6 3 2 5 3 4 3 7 5 1.5 1 2 1.5 3 2 2 H 0.5 I J Find the probability that concert can be held on 15th day or before