Question: Immediate Predecessor(s) Activity A B D E F G H 1 A B B E, F D G H Time (days) 5 2 4 5

Immediate Predecessor(s) Activity A B D E F G H 1
Immediate Predecessor(s) Activity A B D E F G H 1 A B B E, F D G H Time (days) 5 2 4 5 5 5 2 3 u Nuru ANU 3.5 Using AOA, diagram the network described below for Sarah McComb's construction project. Calculate its critical path. How long is the minimum duration of this network? Time Time Activity Nodes (weeks) Activity Nodes (weeks) J 1-2 10 N 3-4 2 K 1-3 8 0 4-5 7 L 2-4 6 3-5 5 M 2-3 3