Question: Immediate Predecessor(s) Activity A B D E F G H A B B C, D D, E G, F Time (Weeks) 3 4 6 9

Immediate Predecessor(s) Activity A B D E F G H A

Immediate Predecessor(s) Activity A B D E F G H A B B C, D D, E G, F Time (Weeks) 3 4 6 9 6 6 8 9 Earliest Start Earliest Finish Latest Start Latest Finish Slack Activity A B D E F G H a. Draw a network for this project. E.g., take a snap shot of your writing or PPT drawing and paste it in the word doc (40 points) b. Make a forward pass and a backward pass to determine ES, EF, LS, LF, and slack, and complete the table. (25 points) c. What are the critical path and the project completion time? (20 points)