Question: Immediate Predecessor(s) Time Activity (weeks) A 7 B 8 Activity E Time (weeks) 5 7 Immediate Predecessor(s) B B C, E DF 2 10 A

Immediate Predecessor(s) Time Activity (weeks) A

Immediate Predecessor(s) Time Activity (weeks) A 7 B 8 Activity E Time (weeks) 5 7 Immediate Predecessor(s) B B C, E DF 2 10 A A D 3 6 a) [4 pts] Compute Dave's earliest start (ES) and earliest finish (EF), latest finish (LF), and latest start (LS) times by filling out the following diagram: C 2 A G 7 10 D 3 Start End E 5 B H 8 6 F 7 b) [2 pts] Compute the duration of the whole project. weeks. c) (2 pts] Compute slack for each activity. Activity Slack A B D E F G H d) [2 pts) Identify critical activities