In 2 0 2 4 , the Westgate Construction Company entered into a contract to construct a
Fantastic news! We've Found the answer you've been seeking!
Question:
In the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $ The road was completed in Information related to the contract is as follows:
Cost incurred during the year $ $ $
Estimated costs to complete as of yearend
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
a In the journal below, complete the necessary journal entries for the year credit Cash Materials, etc. for construction costs incurred
b In the journal below, complete the necessary journal entries for the year credit Cash Materials, etc. for construction costs incurred
c In the journal below, complete the necessary journal entries for the year credit Cash Materials, etc. for construction costs incurred