Question: In 2016, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the PAC). The PAC contract price is
In 2016, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the PAC). The PAC contract price is $150 million. Chicago recognizes revenue on this contract over time according to percentage of completion. At the end of 2016, the following financial statement information indicated the results to date for the PAC (missing items denoted by letter):
INCOME STATEMENT:
Revenue $w million
Cost of Construction 35 million
Gross Profit $x million
Balance Sheet:
Accounts recievable from construction billings $14 million
Construction in progress $50 million
Less: Billings on construction ($y million)
Net billings in excess of construction in progress $z million
CASH FLOW STATEMENT:
Cash collections $46 million
REQUIRED:
Compute the following, placing you answer in the spaces provided and showing supporting computations below:
Item to compute Answer
Total revenue recognized during 2016 (w):
Gross profit recognized during 2016 (x):
Billings on construction (y):
Net billings in excess of construction in progress (z):
Calculate the percentage of PAC that was completed during 2016: