Question: In 2017, Chik-Fil-A signed a contract valued at $900K. It was estimated that $650K would be required to complete the work requested. In 2017, a

In 2017, Chik-Fil-A signed a contract valued at $900K. It was estimated that $650K would be required to complete the work requested. In 2017, a total of $100K in costs had been accumulated. In 2018, the area in which the work was performed received an unexpected ice storm that knocked out power for two weeks. This caused the total estimated costs to complete the project to increase to $1M due to contingencies placed within the contract. An additional $400K costs was accumulated during 2018.

Prepare the journal entries required in 2017 and 2018.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Explanation i It is assumed that outcome o the contract is reasonably assured ii Percentage compl... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!