Question: In 2018, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the
In 2018, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows:
2018 | 2019 | 2020 | |
Costs incurred during the year | $238,000 | $319,600 | $105,000 |
Estimated costs to complete | 357,000 | 139,400 | -0- |
Partial billings | 260,000 | 210,000 | 380,000 |
Collections | 240,000 | 200,000 | 410,000 |
Assuming the performance obligation is satisfied over time, what would be the gross profit in 2018?
Group of answer choices
$255,000
$425,000
$260,000
$102,000
Step by Step Solution
There are 3 Steps involved in it
Answer Gross profit Recognised in year 2018 is 102000 Explanation percentage of completion Cost incu... View full answer
Get step-by-step solutions from verified subject matter experts
