Question: In 2022, Leo construction will work on a residential project that lasts 4 months. The direct costs of the residential project are shown in





In 2022, Leo construction will work on a residential project that lasts 4 months. The direct costs of the residential project are shown in the following bar chart. Assuming $5,000 indirect cost per month, and 12% markup. If the retainage is 8% throughout the project, finance charge is 1% per month, and payments will be billed at the end of the month and will be received one month later. Fill out the table and find out the peak financial requirement as well as the net profit of the project. $160,000 $120,000 B $90,000 C $80,000 D 1 2 3 4