Question: In 3-point estimation for activity duration, what are the three estimates typically used to calculate the expected duration? Question 9 options: Optimistic, pessimistic, and realistic

In 3-point estimation for activity duration, what are the three estimates typically used to calculate the expected duration? Question 9 options: Optimistic, pessimistic, and realistic estimates. Best-case, worst-case, and average estimates. Fast, normal, and slow estimates. Preliminary, intermediate, and final estimates