Question: in a 4 0 - cycle worker - machine time study, operator time is 0 . 6 0 minutes for each cycle and machine time

in a 40-cycle worker-machine time study, operator time is 0.60 minutes for each cycle and machine time is 1.40 minutes for each cycle. The employee performance rating is 115% and the additional times in an 8-hour shift are personal need time, 30 minutes, fatigue share 20 minutes, delay share 30 minutes. Calculate the standard time for combined worker machine operation.