Question: In a certain week, a production schedule for a certain department shows the following parts being produced: 576 parts of type A, 1,231 parts of
In a certain week, a production schedule for a certain department shows the following parts being produced: 576 parts of type A, 1,231 parts of type B, 464 parts of type C, and 1,234 parts of type D. The respective production times for these parts are the following: TpA = 3.14 min, TpB = 3.39 min, TpC = 2.79 min, and TpD = 5.11 min. Determine the workload for this department in hours per week (2 decimal points).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
