Question: In a change request, what is a corrective action? A planned action that brings the project back into alignment with the Project Management Plan A
In a change request, what is a corrective action? A planned action that brings the project back into alignment with the Project Management Plan A planned action to modify a nonconforming product or subcomponent An activity that ensures that a future activity will align with the project management plan Changes to formally controlled project documents, plans, matrices, and registers to reflect current ideas, content, or plans
Step by Step Solution
There are 3 Steps involved in it