Question: In a construction project, Task A involves laying the foundation, while Task B involves constructing the walls. Task B cannot begin until the foundation is

In a construction project, Task A involves laying the foundation, while Task B involves constructing the walls. Task B cannot begin until the foundation is completed, and it must finish when the wall construction is done. What type of relationship does this illustrate in project management? Question 7 options: Finish to Finish (FF) Start to Finish (SF) Finish to Start (FS) Start to Start (SS)