Question: In a construction project, the duration to complete a Watershed management task is given as follows. Optimistic = 1 0 weeks; Most likely = 2

In a construction project, the duration to complete a Watershed management task is given as follows.
Optimistic =10 weeks; Most likely =20 weeks Pessimistic =50 weeks.
If the activity follows a triangular distribution function as shown below, which one of the following is correct?