Question: In a continuous review system, if the average demand during leadtime is 100 units and the safety stock has been determined to be 15 units,
In a continuous review system, if the average demand during leadtime is 100 units and the safety stock has been determined to be 15 units, what should be the reorder point?
Group of answer choices
15
100
115
1500
None of the above