Question: In a cost-plus contract, the Guaranteed Maximum Cost (GMC) is Rs. 50 lakhs. The percentage payable to the contractor over and above his actual cost

In a cost-plus contract, the Guaranteed Maximum Cost (GMC) is Rs. 50 lakhs. The percentage payable to the contractor over and above his actual cost towards his profits and overheads is 15%. The Shared Savings Provision(SSP) in the contract is in the ratio of 50:50. What amount will be paid to the contractor over and above his actual cost if the actual cost of completion of the project is:

  1. Rs. 40 lakhs.
  2. Rs. 50 lakhs
  3. Rs. 60 lakhs.