Question: In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for
In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for the next couple of days. The backlog item is a prerequisite for a feature expected by users in the next sprint review.What should the project lead doA Work with the product owner to change the priorities in the sprint backlog.B Work with the product owner to inform the users that the feature is delayed.C Ask the development manager to provide a replacement for a couple of days.D Ask the developer to postpone the leave until the backlog item is delivered.