Question: In a EOQ model, the supplier lead time L=2 weeks and the optimal cycle time T = 2.5 weeks. Assuming the demand rate is D
In a EOQ model, the supplier lead time L=2 weeks and the optimal cycle time T =
2.5 weeks. Assuming the demand rate is D = 260 units/year, what is the optimal reorder
point? (Assume that one year = 52 weeks)
A) 5
B) 10
C) 520
D) 650
E) 130