Question: In a EOQ model, the supplier lead time L=2 weeks and the optimal cycle time T = 2.5 weeks. Assuming the demand rate is D

In a EOQ model, the supplier lead time L=2 weeks and the optimal cycle time T =

2.5 weeks. Assuming the demand rate is D = 260 units/year, what is the optimal reorder

point? (Assume that one year = 52 weeks)

A) 5

B) 10

C) 520

D) 650

E) 130