In a factory the basic wages rate is Rs.10 per hour and overtime rate as follows Before
Fantastic news! We've Found the answer you've been seeking!
Question:
In a factory the basic wages rate is Rs.10 per hour and overtime rate as follows
Before and after normal working hours175% of basic wage rate
Sunday and holidays225% of basic wage rate
During the previous year the following hours were worked:
Normal time1,00,000 hours
Overtime before and after working hours20,000 hours
Overtime on sundays and holidays5,000 hours
Total1,25,000
The following hours have been worked on job Z
Normal working hours1,000 hours
Overtime before and after100 hours
Sunday and holidays25 hours
1,125 hours
Required :
Calculate the labour cost chargeable to job Z and overhead in each of the following instances
- Where overtime is worked regularly throughout the year as policy due to labour shortage
- Where overtime is worked irregularly to meet the requirements of production
- Where the overtime is worked at the request of the customer to complete the job
- Where overtime is worked due to breakdown of machinery.