Question: In a flexible budget performance report, Question 1 options: the budget is based on the activity that was expected at the beginning of the period.
In a flexible budget performance report,
Question 1 options:
|
| the budget is based on the activity that was expected at the beginning of the period. |
|
| the budget is adjusted to the actual activity for the period. |
|
| budgeted fixed costs are different than they would be in a static budget. |
|
| only the unfavorable variances are recorded for managers to explore. |