Question: In a helpdesk organization that is operating 2 4 / 7 , the next shift cannot start until the current shift finishes is an example

In a helpdesk organization that is operating 24/7, the next shift cannot start until the current shift finishes is an example of which precedence diagramming method relationship ? a) Finish to Finish (FF) b) Start to Start (SS) Start to Finish (SF) d) None of the choices e) Finish to Start (FS)