Question: In a linear sequence of operations A , B , C , D , and E , each operation receives one unit from raw materials
In a linear sequence of operations A B C D and E each operation receives one unit from raw materials or the prior operation and outputs one unit. Operation A produces units a day, operation B produces units a day, operation C produces units per day, operation D produces units a day and operation E final assembly, produces units a day.
Operation E receives inputs from other parts of the process that do not pass through the constraint and it sends its output to shipping.
Demand is for units a day.
Where is the rope?
In a linear sequence of operations A B C D and E each operation receives one unit from raw materials or the prior operation and outputs one unit. Operation A produces units a day, operation B produces units a day, operation C produces units per day, operation D produces units a day and operation E final assembly, produces units a day.
Operation E receives inputs from other parts of the process that do not pass through the constraint and it sends its output to shipping.
Demand is for units a day.
Where is the rope?
The rope goes from operation B to the raw materials used by the gateway operation.
The rope goes from operation A to operation E
The rope goes from operation E to operation A
The rope goes from operation B to the raw materials used for the drum operation.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock