Question: . In a manufacturing process, following standards apply: Standard prices: Raw Material A Rs 10/Kg and B Rs 50/kg Standard Mix 75% of A and

. In a manufacturing process, following standards apply:

Standard prices: Raw Material A Rs 10/Kg and B Rs 50/kg

Standard Mix 75% of A and 25% of B (By weight)

Standard output 90% of the raw material (in weight)

In a particular period, actual costs, usages and output were as follows:

4400 kg of A costing Rs 46,500

1600 kgs of B costing Rs 78,500

Output was 5670 kgs of the product.

The budgeted output of the period was 7200 kgs.

Calculate all material variances.

. In a manufacturing process, following standards apply:

Standard prices: Raw Material A Rs 10/Kg and B Rs 50/kg

Standard Mix 75% of A and 25% of B (By weight)

Standard output 90% of the raw material (in weight)

In a particular period, actual costs, usages and output were as follows:

4400 kg of A costing Rs 46,500

1600 kgs of B costing Rs 78,500

Output was 5670 kgs of the product.

The budgeted output of the period was 7200 kgs.

Calculate all material variances.

.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!