Question: In a master production schedule ( MSP ) the quantities represent demand, which can be actual customer orders and demand forecasts the feasibility is guaranteed

In a master production schedule (MSP)
the quantities represent demand, which can be actual customer orders and demand forecasts
the feasibility is guaranteed from the start, since the MSP works within the constraints of the aggregate production plan
all the quantities represent, directly or indirectly, finished products
some companies set a fence time, within which no more changes to the MSP are allowed.
 In a master production schedule (MSP) the quantities represent demand, which