Question: In a master schedule, the planning horizon is often separated into a series of time periods called Multiple Choice firm, fixed, and frozen. time buckets.
In a master schedule, the planning horizon is often separated into a series of time periods called
Multiple Choice
firm, fixed, and frozen.
time buckets.
pegging.
stacked lead times.
lead times.