Question: In a network (built with normal task times), the critical path indicates: the shortest possible time in which the project can be done the longest

In a network (built with normal task times), the critical path indicates:

  1. the shortest possible time in which the project can be done
  2. the longest possible duration of the project
  3. The expected variability in the project duration
  4. All of the above
  5. None of the above