Question: In a network (built with normal task times), the critical path indicates: the shortest possible time in which the project can be done the longest
In a network (built with normal task times), the critical path indicates:
- the shortest possible time in which the project can be done
- the longest possible duration of the project
- The expected variability in the project duration
- All of the above
- None of the above