Question: In a PERT network, non - critical activities that have little slack need to be monitored closely: Select one: a . because they have a
In a PERT network, noncritical activities that have little slack need to be monitored closely:
Select one:
a because they have a high risk of not being completed.
b because PERT treats all activities as equally important.
c because they are causing the entire project to be delayed.
d because nearcritical paths could become critical paths with small delays in these activities.
e because slack is undesirable and needs to be eliminated.